Close Menu
    What's Hot

    What Is The Burj Khalifa Used For?

    August 23, 2026

    How Long Did It Take To Build The Burj Khalifa?

    August 22, 2026

    Burj Khalifa Photo Spots: 10 Best Places To Take Photos in Dubai

    August 21, 2026
    Facebook X (Twitter) Instagram
    • About Us
    • Contact Us
    • Privacy Policy
    Facebook X (Twitter) Instagram Pinterest VKontakte
    In Downtown Dubai
    • Home
    • Visitor Guide
    • Getting There
    • Shopping
    • Dining
    • Hotels
    • Things to Do
    In Downtown Dubai
    Home » How Long Did It Take To Build The Burj Khalifa?
    Downtown Dubai

    How Long Did It Take To Build The Burj Khalifa?

    Lala Din MuhammadBy Lala Din MuhammadAugust 22, 20266 Mins Read4 Views
    Facebook Twitter Pinterest LinkedIn Tumblr Email
    Burj Khalifa Completion Date
    Share
    Facebook Twitter LinkedIn Pinterest Email

    The Burj Khalifa took about six years to build. It was one of the most ambitious construction projects in Dubai and required years of planning, engineering, and large scale construction work.

    The tower’s height and unusual design created major challenges for the teams working on the project.

    Building such a tall structure required careful work at every stage, from the deep foundation to the upper sections of the tower.

    Here is a closer look at how the Burj Khalifa was built and what happened during those six years.

    Burj Khalifa Construction Timeline

    The Burj Khalifa did not rise to 828 metres in one step. Construction moved through several stages, starting below ground and then moving up through the main structure, exterior cladding, and spire.

    Here is the main construction timeline:

    DateConstruction Milestone
    January 2004Excavation started
    February 2004Piling started
    March 2005Superstructure construction started
    June 2006Level 50 reached
    January 2007Level 100 reached
    July 2007Level 141 reached and became the world’s tallest building
    September 2007Level 150 reached
    April 2008Level 160 reached
    January 2009Spire pipe jacking was completed and the tower topped out
    September 2009Exterior cladding was completed
    January 4, 2010Official inauguration

    The timeline shows how quickly the tower gained height after the foundation stage. It reached Level 100 in January 2007 and Level 141 only six months later. By April 2008, the structure had reached Level 160.

    How Was The Burj Khalifa Built?

    The Burj Khalifa was built in several major stages, from the foundation to the 828 metre structure and its exterior. The main construction work included:

    • Foundation: Workers began excavation in January 2004 and built a deep foundation with 192 piles and a 3.7 metre thick concrete mat
    • Main structure: The superstructure started in March 2005 and used a Y shaped design with a buttressed core to improve stability
    • Concrete work: About 330,000 cubic metres of concrete were used, with concrete pumped to heights of about 601 metres during construction.
    • Exterior: The façade used about 103,000 square metres of glass and 15,500 square metres of stainless steel. Cladding was completed in September 2009.
    • Spire: The final spire brought the tower to its full height of 828 metres. The tower topped out in January 2009.

    These stages took place over several years and required precise planning at every level. The foundation, structural system, exterior, and spire each played a different role in completing the Burj Khali

    Who Built The Burj Khalifa?

    Emaar Properties developed the Burj Khalifa, while Skidmore, Owings & Merrill, known as SOM, handled the architectural and engineering work. Adrian Smith served as the designer.

    The main project roles were:

    • Developer: Emaar Properties PJSC
    • Architects and engineers: Skidmore, Owings & Merrill
    • Designer: Adrian Smith
    • Main contractor: Samsung Corporation
    • Project and construction manager: Turner International

    Samsung Corporation was the main contractor listed for the project. The wider construction involved many specialist companies and teams working across different parts of the project.

    How Fast Was The Burj Khalifa Built?

    The Burj Khalifa gained height quickly after the main structure began in 2005. The construction milestones show the pace clearly, with major levels reached within relatively short periods.

    The main height milestones were:

    • Level 50: June 2006
    • Level 100: January 2007
    • Level 141: July 2007
    • Level 150: September 2007
    • Level 160: April 2008
    • Full structural height: January 2009

    The structural construction followed a cycle of roughly one floor every three days during the main building phase.

    This pace applied to the repeated structural work and did not mean the complete building, including its exterior and interior, was finished every three days.

    Why Did It Take Six Years to Build the Burj Khalifa?

    Building an 828 metre tower required several major construction stages. The work began with a deep foundation and then moved into a tall reinforced concrete structure, exterior cladding, and the final spire.

    Several factors affected the construction period:

    • The foundation required deep piles and a large reinforced concrete mat
    • The main structure had to support a tower reaching 828 metres
    • Engineers had to account for strong wind forces at great heights
    • High performance concrete had to be pumped hundreds of metres above ground
    • The exterior required a large quantity of glass, aluminium, and stainless steel
    • The spire had to be constructed and raised at the top of the tower
    • Exterior work continued after the main structure reached its final height

    Wind engineering also played a major role. The Y shaped plan and stepped form helped reduce wind forces, while more than 40 wind tunnel tests examined the tower’s response to wind, heat, and vibration.

    What Materials Were Used To Build the Burj Khalifa?

    The Burj Khalifa uses large quantities of concrete, reinforced steel, glass, and stainless steel. These materials form the main structure and much of the exterior façade.

    The main material figures are:

    • Concrete: 330,000 cubic metres
    • Reinforced steel: 39,000 tonnes
    • Glass: 103,000 square metres
    • Stainless steel: 15,500 square metres

    These quantities show the scale of the construction operation. The materials had to be moved, installed, and checked as the tower continued to rise.

    How Many Workers Built the Burj Khalifa?

    More than 12,000 workers were involved at the peak of construction. The project recorded about 22 million man hours in total.

    The workforce included people working on foundation construction, concrete, steel reinforcement, structural work, façade installation, engineering, site management, and other specialist tasks.

    The large workforce allowed different parts of the project to progress at the same time. Even with thousands of workers involved, the complete construction period still covered about six years from the start of excavation to the official inauguration.

    How Much Did It Cost To Build the Burj Khalifa?

    The estimated cost of the Burj Khalifa was about US$1.5 billion. This figure refers to the tower itself and should not be confused with the cost of the wider Downtown Dubai development.

    The cost covered the tower’s major construction work, including its foundation, structural system, façade, building services, and finishing work.

    Conclusion

    The Burj Khalifa’s construction was a long, carefully planned process that moved through several stages before the building was ready for use.

    Looking at the timeline helps explain why the project required several years rather than being completed in a short period.

    The biggest takeaway is that building a skyscraper of this scale involved much more than reaching its final height.

    Each stage had to connect with the next, from early site work to structural construction and final preparation.

    This timeline gives you a clearer picture of what happened during the years it took to build one of Dubai’s most famous landmarks.

    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email
    Lala Din Muhammad
    Lala Din Muhammad
    • Facebook
    • Instagram

    Lala is the founder of In Downtown Dubai, a website that publishes guides about Dubai Mall. His work focuses on shopping, dining, attractions, events, and visitor tips inside the mall. He researches information using mall directories, business listings, and tourism sources to create clear guides that help visitors understand what to see, where to eat, and how to plan their visit to Dubai Mall.

    Related Posts
    What Is The Burj Khalifa Used For?
    August 23, 2026
    Burj Khalifa Photo Spots: 10 Best Places To Take Photos in Dubai
    August 21, 2026
    Burj Khalifa Fireworks: Time, Best Viewing Spots, & Tips
    August 13, 2026
    10 Interesting Facts About Burj Khalifa You May Not Know
    August 10, 2026
    Lala Din Muhammad - Founder of In Downtown Dubai

    Lala Din Muhammad

    Founder & Editor at In Downtown Dubai

    Lala is the founder of In Downtown Dubai, a website that publishes clear guides about Dubai Mall. His work covers shopping, dining, attractions, events, and visitor tips to help people understand what to see and how to plan their visit inside one of Dubai’s largest destinations.

    • Research based Dubai Mall guides
    • Shopping, dining, and attraction information
    • Visitor tips and practical details
    • Content reviewed and updated regularly
    Facebook profile Instagram profile
    Recent Posts
    What Is The Burj Khalifa Used For?
    August 23, 2026
    How Long Did It Take To Build The Burj Khalifa?
    August 22, 2026
    Burj Khalifa Photo Spots: 10 Best Places To Take Photos in Dubai
    August 21, 2026
    Burj Khalifa Fireworks: Time, Best Viewing Spots, & Tips
    August 13, 2026

    Get Dubai Mall Updates

    Get the latest Dubai Mall updates, dining spots, shopping news, and helpful tips for your next visit.

    About Us
    About Us

    In Downtown Dubai is your trusted guide for everything happening at Dubai Mall. From shopping and dining to attractions, events, and visitor tips, we share clear and helpful updates to make every visit better.

    Email Us: indowntowndubai@gmail.com

    Our Picks
    What Is The Burj Khalifa Used For?
    August 23, 2026
    How Long Did It Take To Build The Burj Khalifa?
    August 22, 2026
    Burj Khalifa Photo Spots: 10 Best Places To Take Photos in Dubai
    August 21, 2026
    Top Dubai Mall Attractions
    • Dubai Mall Aquarium & Underwater Zoo
    • KidZania Dubai Mall
    • VR Park Dubai Mall
    • Dubai Dino in Dubai Mall
    • Hysteria Dubai Mall
    • Trampo Extreme Dubai Mall
    • Reel Cinema Dubai Mall
    • Dubai Mall Ice Rink
    • Chinatown Dubai Mall
    Facebook X (Twitter) Instagram Pinterest
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Editorial Policy
    © 2026 In Downtown Dubai. All rights reserved.

    Type above and press Enter to search. Press Esc to cancel.